THE Energy Regulatory Commission is running after 13 power generation companies that exceeded the allowable unplanned outage limits and had issued 24 show-cause orders against them.

This is in line with ERC’s crackdown on plant breakdowns that threaten electricity supply and risk driving up power costs.

The ERC said Wednesday that the companies could face fines and other sanctions if investigations confirm violations of mandatory reliability standards, Bilyonaryo reported.

Among those cited were Bac-Man Geothermal Inc., Belgrove Power Corp., Central Azucarera de San Antonio Inc. and CBK Power Co. Ltd.

The list also includes Energy Development Corp., Excellent Energy Resources Inc., Meridian Power Inc., Republic Cement & Building Materials Inc., SPC Island Power Corp., Sunwest Water & Electric Co. Inc., Therma Mobile Inc. and Toledo Power Corp.

The affected facilities span geothermal, hydroelectric, coal, natural gas and diesel power plants.

The orders, issued on Oct. 14, required the firms to explain alleged breaches of prescribed performance benchmarks.

The action follows a compliance review that began on June 11, when the ERC issued notices of noncompliance to 25 generation companies covering outages at 48 generating units.

After reviewing operational records, technical explanations and supporting documents, the regulator found grounds to pursue further proceedings against 13 companies.

The ERC said it was awaiting formal responses to the latest orders before resolving the administrative cases, pledging to uphold due process while continuing to monitor power plant reliability.

Still on power supply, the collapse of a National Grid Corporation of the Philippines (NGCP) transmission tower in Cavite has put the company’s contractor vetting and construction oversight under scrutiny after a firm linked to a Chinese national previously arrested over alleged citizenship fraud was identified as the builder, reported Bilyonaryo on Wednesday.

The tower collapsed Saturday afternoon in Indang, Cavite, damaging a nearby structure, injuring several workers and prompting residents to question whether the steel used was strong enough to support transmission cables installed barely six weeks earlier.

“Baka lalabas sa imbestigasyon, substandard ‘yung ginamit nilang bakal,” a witness told Bilyonaryo News Channel (BNC), citing concerns over the thickness of the steel components.

The cause of the collapse remains under investigation, with no official finding that substandard materials, faulty construction or contractor negligence contributed to the incident.

A BNC source identified Maxipro Development Corporation as the contractor behind the collapsed tower. Its major shareholder, Lawrence Ke Sy is a Chinese national previously arrested by the Bureau of Immigration over allegations involving fraudulent documents used to support his claim to Filipino citizenship.

The status of the case against Sy remains unclear, and no connection has been established between the citizenship allegations and the tower collapse.

Maxipro’s website lists 17 NGCP projects, including 11 marked as completed, raising questions about how the transmission operator selects contractors, inspects their work and ensures construction standards are met.

Both the NGCP and Maxipro have yet to issue a statement.

NGCP, whose shareholders include Filipino investors led by billionaire Henry “Big Boy” Sy Jr. and China’s State Grid Corporation, operates the Philippines’ electricity transmission network.